Tuesday, December 20, 2011

PC-783, Detroit Contracting (DCI) Submits Low Bid on Electrical Ductbank Repair Project

Detroit Contracting, Inc. (DCI) submitted the low bid earlier this afternoon on the project known as DWSD Contract PC-783, "Underground Electrical Ductbank Repair and EB-1, EB-2 and EB-10 Primary Service Improvements at WWTP and Replacement of Selected Roads at WWTP."

1.   Detroit Contracting - - - - - - $26,921,543
2.  Lakeshore Engineering - - -  $27,107,427
3.  Weiss Construction - - - - - $27,620,000*
4.  Walbridge - - - - - - - - - - - - $28,488,000
5.  Motor City Electric - - - - - - $29,839,970

The electrical portion of the project consists of installation of a new 120KV electrical feeder from DTE, replacement and addition of transformers, switchgears, MCC's and motor starter line ups. In addition, other electrical work including lighting, ground and lightning protection for buildings EB-1, EB-2 and EB-10.

For more about DWSD Update, click here

*Update (2/22): Weiss Construction was awarded this contract by the Water Board on February 22, 2012 (here). 