Lakeshore Engineering submitted the low bid earlier this afternoon on the project known as DWSD Contract PC-786, Rouge River Outfall No. 2 (RRO-2) Segment 1, WWTP Modifications:
1. Lakeshore Engineering - - - $11,855,749*
2. Walbridge Aldinger - - - - - $12,970,000**
3. Walsh Construction - - - - - $13,117,000
4. Weiss Construction - - - - - $13,391,000
5. Detroit Contracting - - - - - $14,021,000
6. L. D'Agostini & Sons - - - - $14,702,250
7. O'Laughlin Construction - $15,232,600
This project was previewed at a June 22, 2011 public hearing and reported here.
For more about DWSD Update, click here.
* Update (11/22): DWSD Update has learned that Lakeshore Engineering asked the City of Detroit to retract its bid on this project in a letter dated November 17, 2011.
** Update (12/21): Earlier this afternoon, at a Special Meeting, the Board of Water Commissioners approved a contract with Walsh Construction for $13,117,000. This followed adoption by the Water Board of a resolution suspending Walbridge Aldinger, and 13 other contractors, for a period of 3 years.
* Update (11/22): DWSD Update has learned that Lakeshore Engineering asked the City of Detroit to retract its bid on this project in a letter dated November 17, 2011.
** Update (12/21): Earlier this afternoon, at a Special Meeting, the Board of Water Commissioners approved a contract with Walsh Construction for $13,117,000. This followed adoption by the Water Board of a resolution suspending Walbridge Aldinger, and 13 other contractors, for a period of 3 years.
No comments:
Post a Comment