Walsh Construction Submits Low Bid on Springwells Upgrade Project (SP-563) (UPDATED)

Walsh Construction submitted the low bid earlier this afternoon on the project known as DWSD Contract SP-563 “Springwells Water Plant Rehab Project.” 
  1. Walsh Construction . . . . . . . .$75,899,000 
  2. Weiss Construction. . . . . . . . $81,676,000 
  3. Christman Co. . . . . . . . . . . . . $85,728,000
  4.  Barton Malow. . . . . . . . . . . . . $86,695,000
The Springwells job was originally advertised in April. The bid opening was delayed several times before today.

Update (9/26): The Board of Water Commissioners today approved a contract with Walsh Construction for this project for $75,899,000 and a duration of 1,710 calendar days. 