Thursday, December 3, 2009

Oakland-Macomb Interceptor Repair: Ric-Man Construction Scores First 2 Contracts

The first two contracts for repair of the Oakland-Macomb Interceptor were bid on November 23 and 24th and Ric-Man Construction was read low bidder on both projects.

OMI Contract No. 1

  • Ric-Man Construction       $12,486,880 
  • Jay Dee Contractors          $12,821,800
  • Dan’s Excavating               $14,488,800

OMI Contract No. 2  

  • Ric-Man Construction      $16,338,600 
  • Jay Dee Contractors        $18,814,000 
  • Dan’s Excavating             $20,973,000