There were four bidders on this project. The as-read bids are as follows:
- Weiss Construction . . . $20,335,000.00
- Walsh Construction . . . $21,363,291.18
- Tooles/DCI, JV . . . . . . . $21,619,256.74
- DeMaria Building Co. . $21,768,736.77
For more about DWSD Update, click here.
Update (8/28): The Board of Water Commissioners voted today 6-0 to approve the award of Contract PC-789 to Weiss Construction for $20,335,000 and a contract duration of 1,350 calendar days.