Monday, July 22, 2013

Weiss Construction Submits Low Bid on Pump Station 1 Upgrades, PC-789

Weiss Construction Co., LLC submitted the low bid on July 16, 2013 for the project known as Pumping Station 1 Rack & Grit and MPI 1 & Jefferson Sampling Stations Improvements,” DWSD Contract No. PC-789. 

 There were four bidders on this project. The as-read bids are as follows:
  1. Weiss Construction . . . $20,335,000.00
  2. Walsh Construction . . . $21,363,291.18
  3. Tooles/DCI, JV . . . . . . . $21,619,256.74
  4. DeMaria Building Co. .  $21,768,736.77
Even after price equalization, Weiss will be low bidder.

For more about DWSD Update, click here.

Update (8/28): The Board of Water Commissioners voted today 6-0 to approve the award of Contract PC-789 to Weiss Construction for $20,335,000 and a contract duration of 1,350 calendar days.