Earlier today, Inland Waters Pollution Control submitted the low bid on the Oakland Macomb Interceptor Drain (OMID) Contract 3, Re-Bid.
1. Inland Waters - - - - - - - - $17,965,840
2. Lanzo Lining Services - - - $18,347,000
3. Jay Dee Contractors - - - $21,556,900
As we noted here, bids for Contract 3 were originally received on July 19, 2011, but thrown out because they reportedly exceeded the Engineer's Estimate. Macomb County officials denied their decision was motivated by the lawsuit they had filed against Inland Waters and 39 other contractors on July 18, 2011. When the bids were opened this morning, the Engineer's Estimate was reported to be $20,195,000.
For more about DWSD Update, click here.
1. Inland Waters - - - - - - - - $17,965,840
2. Lanzo Lining Services - - - $18,347,000
3. Jay Dee Contractors - - - $21,556,900
As we noted here, bids for Contract 3 were originally received on July 19, 2011, but thrown out because they reportedly exceeded the Engineer's Estimate. Macomb County officials denied their decision was motivated by the lawsuit they had filed against Inland Waters and 39 other contractors on July 18, 2011. When the bids were opened this morning, the Engineer's Estimate was reported to be $20,195,000.
For more about DWSD Update, click here.